Project Description

  • Preparation of project viability analysis report based on pre. Feasibility study; projected tariff and financial model of Project.
  • Assistance in preparation of SOQ’s to obtain the 1.01 from PPIB.
  • Preparation of RFP and ranking report for selection of consultant for feasibility study.
  • Supervision of feasibility study conducted by Scott Wilson and assisted in approval of feasibility study by panel of experts of PPIB.
  • Preparation of tariff model and tariff petition of the Project.
  • Preparation and maintenance of project accounts & assistance in due diligence of project by various stakeholders.
  • Negotiated the tariff with NTDC and got it approved by NTDC Board. Submission of petition to NEPRA is in Process.
  • Prepared a detailed financial model of the Project based on tariff agreed by NTDC.
  • Registered the Project as proposed CDM activity with UNFCCC.